Strategies for project scheduling with alternative subgraphs under uncertainty: similar and dissimilar sets of schedules

Servranckx, T; Vanhoucke, M; (2019) Strategies for project scheduling with alternative subgraphs under uncertainty: similar and dissimilar sets of schedules. European Journal of Operational Research , 279 (1) pp. 38-53. 10.1016/j.ejor.2019.05.023. Green open access

[thumbnail of Servranckx and Vanhoucke, EJOR, 2019b - Working Paper Version.pdf]
Preview
Text
Servranckx and Vanhoucke, EJOR, 2019b - Working Paper Version.pdf - Accepted Version

Download (1MB) | Preview

Abstract

In the resource-constrained project scheduling problem with alternative subgraphs (RCPSP-AS), we model alternative execution modes for work packages in the project. In contrast to the traditional RCPSP, the project network consists of different alternative work packages. To that purpose, the scheduling problem selects the best possible alternatives for the construction of the baseline schedule. On top of that, several back-up schedules are created in order to cope with unexpected changes along the project progress. In the presence of uncertainty, we can then switch between these alternative schedules at different decision moments in order to bring the project back on track. The alternative schedules are combined in a set of schedules that should be constructed by the project manager prior to project execution. We present a computational experiment to investigate the ability of using such a set of schedules in the presence of uncertainty during project execution. The experiments indicate that using a set of schedules outperforms the use of a single schedule, even when the uncertainty level is relatively low. The results also show that the composition of this schedule set is important. Therefore, a degree of schedule similarity is proposed to analyse this composition, and results show that a mix of similar and dissimilar schedules performs best. Finally, we show that the solution quality of each schedule in the set has an impact on the performance of the schedule switches given the project disruptions.

Type: Article
Title: Strategies for project scheduling with alternative subgraphs under uncertainty: similar and dissimilar sets of schedules
Open access status: An open access version is available from UCL Discovery
DOI: 10.1016/j.ejor.2019.05.023
Publisher version: https://doi.org/10.1016/j.ejor.2019.05.023
Language: English
Additional information: This version is the author accepted manuscript. For information on re-use, please refer to the publisher’s terms and conditions.
Keywords: Project scheduling, Alternative subgraphs, Simulation, Scenario analysis
UCL classification: UCL
UCL > Provost and Vice Provost Offices
UCL > Provost and Vice Provost Offices > UCL BEAMS
UCL > Provost and Vice Provost Offices > UCL BEAMS > Faculty of Engineering Science
UCL > Provost and Vice Provost Offices > UCL BEAMS > Faculty of Engineering Science > UCL School of Management
URI: https://discovery.ucl.ac.uk/id/eprint/10122701
Downloads since deposit
169Downloads
Download activity - last month
Download activity - last 12 months
Downloads by country - last 12 months

Archive Staff Only

View Item View Item